The project  Overview

Oliver Boreal was engaged by J.S Contracts (Stockport) ltd. As project mangers for the scheme it was Oliver Boreal’s duty to control all aspects of the building construction.

The project

In November 2007 the team commenced the construction of 64 apartments, retail space and 2 story underground parking. The project commenced with the installation of a concrete piled wall to create the basement, some 51 foot down. With in-situ concrete construction to form the basement structure. The upper build was designed with a lightweight steel frame to accommodate cladding system to complete the envelope. In July 2009 The project was stopped as a result of the bank going into Administration.